Skip to main content

How to File a Possession-Delay Claim Under RERA Section 18 in Gujarat (2026 Guide)

Gujarat buyers facing possession delay can claim interest at SBI MCLR + 2% under Section 18 of the RERA Act, 2016. File at Gujarat Real Estate Regulatory Authority for ₹1,000 per allottee complaint; ₹5,000 if filed by promoter. Statutory disposal target 60 days. Brickplot is independent — no builder commissions.

Section 18 — what it actually says

Section 18 of the Real Estate (Regulation and Development) Act, 2016 is the single most important provision for an allottee whose possession has been delayed. The structure is binary: if the promoter fails to complete or is unable to give possession by the date specified in the registered agreement for sale, the allottee may either (a) withdraw and demand full refund + interest at the prescribed rate, or (b) continue with the project and claim monthly interest until offer of possession.

The “prescribed rate” under RERA Rules of every state is SBI MCLR + 2 percentage points. The Supreme Court in Newtech Promoters & Developers Pvt Ltd v. State of UP (2021) held the Section 18 right is absolute and cannot be diluted by force-majeure clauses, “grace periods”, or contractual waivers. Binding on every state RERA, including Gujarat Real Estate Regulatory Authority.

Gujarat-specific filing process at Gujarat Real Estate Regulatory Authority

  1. Register on the portal. Visit https://gujrera.gujarat.gov.in/. KYC via Aadhaar + PAN; for NRIs, passport + OCI/PIO card.
  2. Open the complaint form. Direct link: https://gujrera.gujarat.gov.in/complaint. Select “Complaint Against Promoter” and “Section 18 — possession delay”.
  3. Pay filing fee. ₹1,000 per allottee complaint; ₹5,000 if filed by promoter.
  4. Upload document set (see next section).
  5. Specify your relief. Section 18(1)(a) (exit + refund + interest) or Section 18(1)(b) (continue + monthly interest).
  6. State-specific quirk. GUJRERA aggressively uses Section 38 deposit orders — requiring developers to deposit 50–100% of disputed amounts during pendency. This materially improves enforcement outcomes.
  7. Tribunal address: Sahyog Sankul, Sector-11, Gandhinagar 382011.

What to attach to your complaint

How interest is calculated

Worked example for Gujarat: principal ₹50 lakh, original possession date 1 January 2024, complaint filed 1 July 2025 (18-month delay), SBI MCLR + 2% ~10.5%/yr → interest payable ~₹7.88 lakh, accruing monthly until offer of possession or refund.

Two practical notes. First, interest accrues from the original registered possession date, not from any “extended” date the developer claims unilaterally. Second, every state RERA — including Gujarat Real Estate Regulatory Authority — has consistently rejected developer attempts to substitute the lower base rate or cap interest at the BBA-stipulated penalty.

Gujarat RERA tribunal hearing process

GUJRERA hearings at Gandhinagar in hybrid mode; cause-list explicitly indicates whether each matter is in person or VC. Sequence: (1) registry scrutinises within 7–14 days; (2) Gujarat Real Estate Regulatory Authority issues notice to promoter, who must file reply within 21–30 days; (3) cause-list published; (4) matter heard across 2–4 hearings if developer raises factual disputes; (5) reserved judgment, then order. GUJRERA averages 4–6 months — among the better-disciplined RERAs.

If aggrieved, appeal lies before Gujarat Real Estate Appellate Tribunal (GREAT), Gandhinagar. within 60 days. The appellate tribunal can stay the order only on developer pre-depositing 30% of awarded amount — preventing frivolous appeals.

Notable Gujarat judgments worth citing

Savvy Group — South Bopal residential delay (2022): GUJRERA ordered interim deposit of ₹15+ crore, eventually converted to refund + interest at MCLR + 2%.

A 2025 GUJRERA order against a Surat residential developer found the promoter had failed to deposit 70% of buyer payments into the mandated escrow. GUJRERA directed immediate Section 38 deposit of ₹12 crore, ordered interest at MCLR + 2%, and forwarded the order to Income Tax Department for escrow-related TDS examination.

Beyond Gujarat-specific orders, every Section 18 complainant should cite Newtech Promoters & Developers Pvt Ltd v. State of UP & Ors, 2021 SCC OnLine SC 1044. The 3-judge SC bench held: (i) RERA applies retrospectively; (ii) Section 18 confers an absolute right; (iii) generic force-majeure pleas (including Covid-stretches) cannot defeat Section 18; (iv) the state RERA has full jurisdiction. Binding on Gujarat Real Estate Regulatory Authority.

Common mistakes that derail claims

Frequently asked questions

What is the filing fee at Gujarat Real Estate Regulatory Authority?

₹1,000 per allottee complaint; ₹5,000 if filed by promoter. Paid online at filing time, receipt auto-attached to complaint record.

Can I file a Gujarat RERA complaint fully online?

GUJRERA aggressively uses Section 38 deposit orders — requiring developers to deposit 50–100% of disputed amounts during pendency. This materially improves enforcement outcomes.

Can an NRI file from abroad?

Yes. NRIs can file directly via portal using e-signature where state allows, or through registered POA holder in India. Attach FEMA-compliant remittance receipts and FIRC for each payment.

Do I need a lawyer to file under Section 18 in Gujarat?

No. RERA Section 31 allows complainant to appear in person. Many Gujarat allottees DIY successfully in straightforward delay cases. Engage counsel if developer raises constitutional or limitation defences.

Can I file the complaint myself (DIY)?

Yes. The portal walks you through KYC, complaint upload, and fee payment. Document set is the same whether DIY or via counsel.

How long does Gujarat Real Estate Regulatory Authority take?

GUJRERA averages 4–6 months — among the better-disciplined RERAs

What happens after the order?

Developer has 45 days to comply or appeal. If unpaid after 45 days, apply for execution before the same authority and revenue-recovery enforcement. Gujarat Real Estate Appellate Tribunal (GREAT), Gandhinagar. hears appeals.

What if I lose at GUJRERA or developer wins on appeal?

Appeal lies before Gujarat Real Estate Appellate Tribunal (GREAT), Gandhinagar. within 60 days. From appellate, further appeal on substantial questions of law lies before the High Court within 60 days. Newtech v. State of UP (2021) protects allottees from technical force-majeure defences at every level.

Verify the regulatory record yourself

Brickplot does not ask you to trust us. Every project review links the primary sources we used.

Need help with your specific possession-delay case?

Brickplot analysts review your agreement, calculate the interest owed under Section 18, and tell you whether filing at Gujarat Real Estate Regulatory Authority is worth it for your case — including document checklist and realistic timelines.

Get a possession-delay review → ₹999

Related Brickplot resources