How to File a Possession-Delay Claim Under RERA Section 18 in Maharashtra (2026 Guide)
Maharashtra buyers facing possession delay can claim interest at SBI MCLR + 2% under Section 18 of the RERA Act, 2016. File at Maharashtra Real Estate Regulatory Authority for ₹5,000 per complaint, the highest in India. Statutory disposal target 60 days. Brickplot is independent — no builder commissions.
Section 18 — what it actually says
Section 18 of the Real Estate (Regulation and Development) Act, 2016 is the single most important provision for an allottee whose possession has been delayed. The structure is binary: if the promoter fails to complete or is unable to give possession by the date specified in the registered agreement for sale, the allottee may either (a) withdraw and demand full refund + interest at the prescribed rate, or (b) continue with the project and claim monthly interest until offer of possession.
The “prescribed rate” under RERA Rules of every state is SBI MCLR + 2 percentage points. The Supreme Court in Newtech Promoters & Developers Pvt Ltd v. State of UP (2021) held the Section 18 right is absolute and cannot be diluted by force-majeure clauses, “grace periods”, or contractual waivers. Binding on every state RERA, including Maharashtra Real Estate Regulatory Authority.
Maharashtra-specific filing process at Maharashtra Real Estate Regulatory Authority
- Register on the portal. Visit https://maharera.maharashtra.gov.in/ ↗. KYC via Aadhaar + PAN; for NRIs, passport + OCI/PIO card.
- Open the complaint form. Direct link: https://maharera.maharashtra.gov.in/en/online-complaint-registration ↗. Select “Complaint Against Promoter” and “Section 18 — possession delay”.
- Pay filing fee. ₹5,000 per complaint, the highest in India.
- Upload document set (see next section).
- Specify your relief. Section 18(1)(a) (exit + refund + interest) or Section 18(1)(b) (continue + monthly interest).
- State-specific quirk. MahaRERA filings need both online submission AND a hard-copy paper-set within 7 days. Most rejections happen because complainants miss the hard-copy step.
- Tribunal address: Housefin Bhavan, Plot C-21, E-Block, BKC, Bandra (East), Mumbai 400051.
What to attach to your complaint
- Allotment letter showing unit number, area, agreed possession date.
- Sale agreement / Builder-Buyer Agreement (registered where stamp-duty rules require).
- Every payment receipt + matching bank statements showing the debit.
- Bank loan sanction + disbursement schedule if you took home-loan finance.
- Possession-promise communications — emails, SMS, WhatsApp, ads, presentation PDFs.
- RERA registration certificate downloaded from the MahaRERA portal — registered possession date is the legal benchmark.
- The latest QPR filed by the promoter on the portal.
- Calculation sheet showing principal paid, dates of each payment, interest at SBI MCLR + 2% claimed up to filing.
How interest is calculated
Worked example for Maharashtra: principal ₹50 lakh, original possession date 1 January 2024, complaint filed 1 July 2025 (18-month delay), SBI MCLR + 2% ~10.5%/yr → interest payable ~₹7.88 lakh, accruing monthly until offer of possession or refund.
Two practical notes. First, interest accrues from the original registered possession date, not from any “extended” date the developer claims unilaterally. Second, every state RERA — including Maharashtra Real Estate Regulatory Authority — has consistently rejected developer attempts to substitute the lower base rate or cap interest at the BBA-stipulated penalty.
Maharashtra RERA tribunal hearing process
Almost entirely virtual via MahaRERA video-conferencing portal. Physical hearings only on bench-listed appeals. Sequence: (1) registry scrutinises within 7–14 days; (2) Maharashtra Real Estate Regulatory Authority issues notice to promoter, who must file reply within 21–30 days; (3) cause-list published; (4) matter heard across 2–4 hearings if developer raises factual disputes; (5) reserved judgment, then order. 60 days under Section 71; MahaRERA averages 3–5 months — fastest in India.
If aggrieved, appeal lies before Maharashtra Real Estate Appellate Tribunal (MREAT), Bandra Kurla Complex, Mumbai. within 60 days. The appellate tribunal can stay the order only on developer pre-depositing 30% of awarded amount — preventing frivolous appeals.
Notable Maharashtra judgments worth citing
Newtech Promoters & Developers Pvt Ltd v. State of UP (2021) — Supreme Court binding precedent now cited in nearly every MahaRERA Section 18 order.
A 2025 MahaRERA order on a Thane mid-rise found the promoter had extended possession date thrice without allottee consent under MOFA. MahaRERA directed interest at SBI Highest MCLR + 2% from December 2020 (a 49-month delay), forfeited maintenance for the delay period, and slapped ₹5L penalty under Section 61.
Beyond Maharashtra-specific orders, every Section 18 complainant should cite Newtech Promoters & Developers Pvt Ltd v. State of UP & Ors, 2021 SCC OnLine SC 1044. The 3-judge SC bench held: (i) RERA applies retrospectively; (ii) Section 18 confers an absolute right; (iii) generic force-majeure pleas (including Covid-stretches) cannot defeat Section 18; (iv) the state RERA has full jurisdiction. Binding on Maharashtra Real Estate Regulatory Authority.
Common mistakes that derail claims
- Missing payment receipts. Reconcile with bank statements at filing time and attach both.
- Weak possession evidence. Anchor to the registered agreement date, not the brochure.
- Wrong tribunal jurisdiction. Filing at the wrong bench or wrong state.
- Naming the wrong respondent. The respondent is the registered promoter on the RERA portal, not the holding company or brand.
- Missing limitation framing. File once you are 6 months past the registered date and developer has not offered possession.
Frequently asked questions
What is the filing fee at Maharashtra Real Estate Regulatory Authority?
₹5,000 per complaint, the highest in India. Paid online at filing time, receipt auto-attached to complaint record.
Can I file a Maharashtra RERA complaint fully online?
MahaRERA filings need both online submission AND a hard-copy paper-set within 7 days. Most rejections happen because complainants miss the hard-copy step.
Can an NRI file from abroad?
Yes. NRIs can file directly via portal using e-signature where state allows, or through registered POA holder in India. Attach FEMA-compliant remittance receipts and FIRC for each payment.
Do I need a lawyer to file under Section 18 in Maharashtra?
No. RERA Section 31 allows complainant to appear in person. Many Maharashtra allottees DIY successfully in straightforward delay cases. Engage counsel if developer raises constitutional or limitation defences.
Can I file the complaint myself (DIY)?
Yes. The portal walks you through KYC, complaint upload, and fee payment. Document set is the same whether DIY or via counsel.
How long does Maharashtra Real Estate Regulatory Authority take?
60 days under Section 71; MahaRERA averages 3–5 months — fastest in India
What happens after the order?
Developer has 45 days to comply or appeal. If unpaid after 45 days, apply for execution before the same authority and revenue-recovery enforcement. Maharashtra Real Estate Appellate Tribunal (MREAT), Bandra Kurla Complex, Mumbai. hears appeals.
What if I lose at MahaRERA or developer wins on appeal?
Appeal lies before Maharashtra Real Estate Appellate Tribunal (MREAT), Bandra Kurla Complex, Mumbai. within 60 days. From appellate, further appeal on substantial questions of law lies before the High Court within 60 days. Newtech v. State of UP (2021) protects allottees from technical force-majeure defences at every level.
Verify the regulatory record yourself
Brickplot does not ask you to trust us. Every project review links the primary sources we used.
- RERA verification: MahaRERA portal ↗ (Brickplot has not yet verified the RERA number — pending)
- Brickplot methodology: 11-axis score · Full rubric · Changelog
Need help with your specific possession-delay case?
Brickplot analysts review your agreement, calculate the interest owed under Section 18, and tell you whether filing at Maharashtra Real Estate Regulatory Authority is worth it for your case — including document checklist and realistic timelines.
Get a possession-delay review → ₹999